N2P Road Work Update, May 21

Work is scheduled Monday-Friday, approx. 7am-5:30pm
Expect 30 Minute Delays

Paradise area:
No work this Friday 5/22
Trench in Paradise parking lot will not be paved this weekend, just compacted.
Trenching crews will continue to work downhill starting again on Tuesday.


Other work:
Tucci starts work in Kautz Creek area on Tuesday 5/26.
Tucci will mobilize equipment and materials into the Park this week.
Next week Tucci will install logs at the Nisqually Entrance.
Next week Tucci will do some spot milling between Nisqually Entrance and Longmire.
The week of June 1, Tucci will begin paving between Nisqually Entrance and Longmire.